County engineer requests multiple change orders and task orders for road projects, and seeks Bradford Road funding
Jun 15, 2026
Jun 15, 2026
Engineer Kevin Russel presented change orders totaling $98,833.15 on two projects, sought authorization to sign Prime AE task orders worth $442,100 in aggregate, and asked the council to consider a $155,500 appropriation for Bradford Road reconstruction.
The full story
County Engineer Kevin Russel outlined several contract actions for the commissioners. He presented change order #1 to the 2026-1 resurfacing contract for $5,614.36 and change order #2 for the Old Highway 111 federal aid PM overlay for $93,218.79; both motions passed 3-0.