Village outlines $2 million first phase for WWTP improvements, seeks grant help

Mar 17, 2026

Mayor Robert Thurston presented a two-phase plan for Wastewater Treatment Plant upgrades, with Phase 1 estimated at $2 million; board authorized staff outreach to the town on EDU cost-sharing and agreed to pursue a hardship-community grant though funding is not guaranteed.

The full story

Mayor Robert Thurston, Jr. told the board the village plans to split the Wastewater Treatment Plant improvement into two projects to meet an October funding deadline and that "Phase 1 would be 2 million." The first phase would focus on a solids building, a belt press and the digester, and the mayor said the village could apply for a hardship-community grant for that work.