County reports progress on Bug Tussel connectivity; New View and Suring sites remain pending

Property & Technology Committee of the Oconto County Board of Supervisors · July 15, 2026

Summary

Oconto County staff said Bug Tussel splicing is complete at the Land Conservation office and the Village of Lena; the New View site awaits conduit installation and Suring Highway work is pending a third-party vendor.

Technology Services Director Melissa Schwaller briefed the committee on connectivity projects undertaken with Bug Tussel. She reported that the Land Conservation office and the Village of Lena have been successfully spliced into the county network. Schwaller said the New View site is waiting for conduit installation and that work at the Suring Highway site is delayed because it depends on a third-party vendor.

County Administrator Richard Heath provided context on the project's background and the county's bonding arrangements with Bug Tussel, and told the committee that additional information will be provided at the Administration Committee meeting. No formal motions were recorded; staff will continue to track vendor dependencies and conduit scheduling.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source