Collin County says modular central plant 92% complete after owner-requested chiller additions
Apr 13, 2026
County building staff reported the modular central utility plant is 92% complete with total cost $31.8 million; owner-requested change orders (including added chillers) have increased change orders to roughly 24.9% of the contract ($6.368 million).
The full story
Sandeep Katuria told commissioners the modular central utility plant is currently at 92% completion. He said the total construction cost for the plant is $31,800,000 and that owner-requested change orders—most notably to add additional chillers—have raised change orders to date to about 24.9% (approximately $6,368,000).