Santa Rosa outlines $14M-plus capital projects including Blue Hole trails, lighting and dam work

Aug 12, 2025

City staff reported multiple capital investments on Aug. 12, 2025: Park Lake Dog Park ($364,000), Blue Hole Trails Phase 1 ($660,000), a $1.2M citywide lighting project, and Power Lake Dam reconstruction ($12.2M). Funding sources include NMDOT, federal Congressional allotments, State Engineer and capital-outlay awards.

The full story

City staff reported a slate of capital projects and their funding sources during the Aug. 12 meeting. The city administrator said Park Lake Dog Park construction begins Aug. 12, 2025 with a budget of $364,000 and that Blue Hole Trails Phase 1 has a $660,000 Congressional direct-spending allocation. A citywide lighting project serving Route 66 and several downtown corridors was listed at $1.2 million and described as federal funding through NMDOT.