Wimberley ISD bond projects progressing, district construction manager reports

Wimberley Independent School District Board of Trustees · July 27, 2026

Summary

AG|CM Ryan Rosborough told the board that bond-funded projects — additions, renovations, roofing and HVAC work, technology upgrades and athletic facility improvements — are progressing as planned, with upcoming milestones scheduled across the district.

Ryan Rosborough, construction manager with AG|CM, presented an update on the WISD 2025 bond projects during the July 27 meeting, reviewing budgets, expenditures, schedules and upcoming milestones. He said work across facility additions, renovations, roofing, HVAC, technology and athletic facility enhancements is underway and that "work continues to progress as planned with additional projects scheduled throughout the coming months."

The presentation included an overview of expenditures to date and forthcoming construction milestones; trustees did not take formal action on the update but were informed that multiple projects remain scheduled through the coming months. The update was presented as an information item and will be monitored in future meetings.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source