Watonwan County reports Watline Trail Phase 2 bridge installed; grading and gravel 50% complete

Aug 4, 2026

Public Works Director Michael McCarty told the board the Watline Trail Phase 2 bridge is installed and grading and gravel placement are about 50% complete; Change Order 4 removed a conflicting timber pile at a cost of $1,920.98.

The full story

Public Works Director Michael McCarty updated the Watonwan County Board on Project SP 083-090-007 (Watline Trail Phase 2), saying the bridge is installed and grading and gravel placement are roughly 50% complete. McCarty said Change Order 4 included removal of a conflicting timber pile at a cost of $1,920.98.