CDOT grant timing means Dylan access work likely needs front‑end engineering in 2027–28, staff says
Summary
Staff told council CDOT funding for Manitou Avenue access improvements tied to Dylan would not be available until about 2029; to keep CDOT reimbursement the city must show engineering progress in 2027–2028.
Get email alerts on the Dylan Project topic
No spam. Unsubscribe anytime.
Public works staff explained that CDOT has given the city a temporary access permit for the Dylan site but programmed the CDOT funds to become available around 2029. Staff recommended advancing engineering and design work in 2027–2028 so that CDOT can reimburse work once funding becomes available; doing so would require the city to front‑fund engineering and potentially use other capital sources to show progress.
City staff also clarified that on‑site phase two work for the Dylan (parking lot and courtyard) is not currently funded in the near term; the CDOT money is restricted to Manitou Avenue access improvements and cannot be used for on‑site Dylan capital. Council asked staff to map which parts of Dylan engineering and construction are eligible for which funding sources and to clarify match requirements and reimbursement timing.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.