Spring Green board endorses two-times fixed fee option after WWTF upgrade review

Village of Spring Green Board of Trustees · August 1, 2026

Summary

After reviewing a User Rate Analysis from Town & Country Engineering, the board reached consensus to pursue a two-times fixed fee sewer-rate structure to support wastewater treatment facility upgrade planning; no formal vote was taken.

On March 11, 2026, the Village of Spring Green Board of Trustees reviewed a User Rate Analysis by Greg Droessler of Town & Country Engineering and came to a consensus to move forward with a “two times fixed fee” option for sewer utility rates to help fund proposed wastewater treatment facility (WWTF) upgrades. The board did not take a formal vote on this item at the meeting.

Droessler presented the preliminary rate options as part of the WWTF upgrade discussion. Trustees discussed the analysis and agreed that the two-times fixed fee option should be pursued further; the transcript records that "No additional action taken." The board did not adopt a rate ordinance and did not set specific dollar amounts at this meeting.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source