Lynn Park backstop project deferred to FY28 after timing concerns
Aug 19, 2026
Committee agreed to keep Lynn Park CIP funds in place rather than transfer them to complete a proposed backstop and fencing project this season; staff expects construction to start July 1, 2027 with about six weeks needed for completion.
The full story
Staff told the committee a recommendation to transfer Lynn Park CIP funds to cover a backstop and fencing project would be delayed because the project could not be completed before the spring sports season. Andrew said the department will keep the funds at Lynn and process the project through the regular CIP cycle for the following fiscal year, with construction tentatively scheduled to start July 1, 2027 and an estimated six-week build time once contractors are engaged.