CDD reports progress on four drainage sites; tree removals and schedule set

River Ridge Community Development District Board of Supervisors · June 23, 2026

Summary

District Engineer Charlie Krebs told the board that all four drainage improvement sites are under construction with pipes installed and grading underway. Palmetto Dunes is expected to finish this week; sod installation in Turnberry is likely the week of July 2 and Oak Run pipe work the week of June 29; a total of 12 trees in Palmetto Dunes will be removed and replaced.

Charlie Krebs reported that all four drainage improvement sites are under construction: sites cleared, silt fences installed and pipes placed. He said fill dirt and grading were completed in Turnberry, Palmetto Dunes is expected to be completed by the end of the week, and sod will likely be installed in Turnberry and Palmetto Dunes the week of July 2. Oak Run pipe installation is scheduled for the week of June 29.

Krebs noted that twelve affected trees in Palmetto Dunes will need to be removed and replaced (mostly slash pines and two red maples) and that six cabbage palms must be removed and replanted in Oak Run. He also said an A/C coolant line was struck by a contractor during clearing and the owner was contacted; the repair will be funded from contingency and Krebs will provide a log of additional costs for the next agenda.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source