Free fill material from Mojave could accelerate pipeline-lowering program, staff says

Feb 26, 2026

Staff told the committee Mojave will deliver tens of thousands of cubic yards of clean fill material for free (48,000 cu yd planned; phase two ~440,000 cu yd expected later), which the district plans to use to raise road profiles and reduce costs on shallow mains.

The full story

Staff described a two-phase soil delivery tied to Mojave’s percolation project that district operations expect to use in a pipeline-lowering program. George said phase one involves roughly 48,000 cubic yards of clean fill, with about 7,000 cubic yards already stored at site 1C near Wilson Ranch, and that phase two could move as much as 440,000 cubic yards later in the year.

Free newsletter

Sign up to keep reading.

Your free newsletter brings you what your city council, county, and school board discussed and decided.

or
Already have an account? Sign in