Borough manager reports paving complete, roundabout utility work ongoing; roundabout construction expected in 2027
Summary
Manager David L. Kramer Jr. told council the 2025 paving program is complete, streetscape conduit and brickwork are underway, utility work for the planned roundabout is ongoing with construction anticipated in 2027, and 12th Street storm-drain prep was completed.
Get email alerts on the Infrastructure Updates topic
No spam. Unsubscribe anytime.
Borough Manager David L. Kramer, Jr. told Monaca Borough Council on June 9 that the 2025 paving program has been completed and that the Streetscape project is progressing with underground conduit installation for future lighting and ongoing brick installation. He said utility work tied to the planned roundabout is underway and that roundabout construction is anticipated in 2027.
Kramer also reported that the Road Department completed storm drain preparation work on 12th Street, including underground improvements near the band room, and that a reported dip near 17th Street has been referred to the responsible utility company for additional repairs. He reminded council that Community Day preparations — including a 5K route and shuttle service from St. John's — are in place and that the RACP grant application is still being finalized.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.