Town engineer reports Phase II, Chub Run and Phase IV sewer projects advancing
Summary
The town's written engineer report said Phase II AMD/AML ROWs are 28 of 34 secured and an environmental assessment was filed 10/23/25; Chub Run extension start is likely delayed past Nov. 1 and Phase IV awaits PSC and DEP approvals to connect at Sandy's Hardware station.
Get email alerts on the Sewer Infrastructure topic
No spam. Unsubscribe anytime.
The town's written engineer report, reviewed at the Oct. 28 meeting, said that right-of-way acquisition for the Phase II AMD/AML project is largely complete (28 of 34 ROWs secured) and that the environmental assessment was submitted to the Office of Surface Mining on Oct. 23, 2025; the engineer said the town is aiming to put the project out for bid by the end of the year.
The report also said the Chub Run sewer extension contractor was scheduled to start around Nov. 1 but that work will likely be delayed until the end of the year. For the Phase IV sewer project, the engineer reported that approvals from the PSC and DEP are still pending for the planned connection to the Sandy's Hardware station.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.