Commission approves five change orders and first pay application for courthouse renovation
Summary
Madison County approved five separate change orders covering helical-pier underpinning, load testing, site lease for contractor trailer, void forms under a basement slab and hazardous-material abatement, and accepted pay application No. 1 for $31,389.40.
County project staff presented five change orders related to the courthouse addition and renovation and commissioners approved each separately. Change orders covered additional helical-pier underpinning ($5,213.40), load testing for piers ($9,731.74), a lease agreement for a contractor trailer ($16,888.89), inclusion of void forms under the basement slab for drainage ($28,741.45) and expanded hazardous-materials abatement after discovery of additional asbestos and lead paint (roughly $30,990.27). The board approved each change order by individual motion and voice vote.
Project staff also presented pay application No. 1 for Jackson Contracting in the amount of $31,389.40 and an architectural invoice for $17,000; commissioners approved payments and asked architectural billing to include more detailed line-item breakdowns in future invoices. On hazardous-materials abatement staff stated, "But it's all gone now and air clearance testing is done. So we are clean," reflecting completion of abatement and clearance testing.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.