Program schedule: $140M under construction, $70M to start soon — staff say cash‑flow report keeps E programs balanced

Aug 19, 2026

Program manager presented that about $140 million of East program projects are in construction and $70 million will start within six months; staff said the cash‑flow report balances cost and revenue and was used historically to pause or restart projects to remain on budget.

The full story

Mr. Hing walked the committee through a dynamic program schedule that is updated monthly and described how the cash‑flow model balances expenditures and projected revenue for each East program.