Change order includes arc‑flash testing and delivery deadline for switch gear
Summary
CPM and staff said the change order requires arc‑flash testing (called out as an OSHA requirement in the discussion) and includes a contractual delivery date for the switch gear to avoid schedule delays.
Get email alerts on the Safety topic
No spam. Unsubscribe anytime.
CPM and staff told directors the change order includes arc‑flash testing and that the contractor would accept liability for testing and delivery. One participant noted arc‑flash testing is an OSHA requirement and suggested Noel as the person to handle that work.
CPM also told the board the change order contains a delivery 'drop‑dead' date (the transcript cites language referencing December 26, 2026) to keep the switch gear on the contractor's schedule. "Our switch gear should be here on time," a CPM representative said when discussing the delivery commitment under the change order.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.