Committee targets late-September RFP release and aims for Dec. 1 contract start
Summary
Staff proposed an RFP schedule (Sept. 25 release, Oct. 6 inquiries deadline, Oct. 16 proposals, Oct. 23 shortlist) and asked the committee to aim for a council action in mid-November so a new lobbying contract could begin Dec. 1.
Get email alerts on the Procurement Timeline topic
No spam. Unsubscribe anytime.
City staff presented a draft procurement timeline and asked the committee if it could move forward with an accelerated schedule to have a contract in place by Dec. 1, the city's usual start date for lobbying services. Brian Head said a sample schedule would include a Sept. 25 release, Oct. 6 deadline for inquiries, an Oct. 16 proposal due date and an Oct. 23 shortlist announcement.
Committee members raised procurement staffing constraints and suggested the possibility of a special meeting to finalize recommendations so the council could act by mid-November. Staff confirmed the current contract ends Nov. 30 and reiterated the city's preference for a Dec. 1 start so lobbyists can monitor pre-filed bills.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.