Drainage projects under way; district expects completion by end of July

Jun 23, 2026

District Engineer reported four drainage sites under construction with staging and tree removals; Palmetto Dunes expected to finish this week, pipe work scheduled the week of June 29 and sod in Turnberry the week of July 2, with overall completion expected by end of July.

The full story

Charlie Krebs told the Board that all four drainage sites are under construction, with sites cleared, silt fences installed and pipe installed at several locations. He reported that Palmetto Dunes is expected to be completed by the end of the week, pipes will be installed in Oak Run the week of June 29 and sod will likely be installed in Turnberry the week of July 2.