Budget update: small variance reported, contingency drawn as team weighs scope trade-offs
Aug 20, 2026
Project staff reported a modest variance (~$55,000) after recent deletions and detailed contingency projections that leave roughly $500,000 available; the committee discussed removing or scaling athletic courts to free funds for reimbursable, accessibility-related items.
The full story
Finance staff reported the project is nearly on budget after recent scope deletions (irrigation and canopy), with a reported variance close to $55,000 — characterized in the meeting as effectively even. The team outlined available allowances (phase 2 ~ $70,000; phase 3 ~ $2.2 million) and a CM contingency that, based on current projections, leaves roughly $500,000 available for forthcoming risks and additions.
Sign up to keep reading.
Your free newsletter brings you what your city council, county, and school board discussed and decided.
Keep reading for free
Create a free account to finish this story and see the video, transcript and key details.
Continue with GoogleContinue with emailAlready have an account? Log in →