Weslaco ISD bond update: $160M program shows progress but multiple projects delayed by engineering and vendors
Nov 17, 2025
Administration told the board about progress across roofing, HVAC, athletic and building‑envelope projects funded by the $160 million bond, but multiple items remain behind schedule; staff estimated roughly $65 million of projects active and cited design/engineering delays, HVAC vendor lead times and poor soil as causes.
The full story
A district project status presentation listed dozens of bond projects — roofs, HVAC upgrades, vestibules, track work, restrooms, and gym demolitions — and estimated about $65 million of the $160 million bond is currently tied to active projects. "It's about roughly about 65 million into our $160 million budget," a presenter told the board.
Sign up to keep reading.
Your free newsletter brings you what your city council, county, and school board discussed and decided.
Keep reading for free
Create a free account to finish this story and see the video, transcript and key details.
Continue with GoogleContinue with emailAlready have an account? Log in →