Evergreen Elementary update: site work done, GMP 3 to come as district says project is on schedule

Aug 17, 2026

A project presenter told the board that site utilities and sidewalks are in place, footings are poured and prefabrication of walls is planned; three contract amendments have been executed and the district will present GMP 3 (full project budget) at the next board meeting.

The full story

A project presenter updated the board on Evergreen Elementary construction, saying early site work is complete, utilities and sidewalks are installed, and crews have poured footings and are preparing to prefab walls on site.