Meredith Court mitigation project costs rising; demolition set to begin in August, council told
Summary
Council member Jennifer Taylor reported that the Meredith Court mitigation project, started about four years ago with PEMA/FEMA involvement, has seen rising costs; a cost analysis is pending and demolition is scheduled to begin in August.
Council member Jennifer Taylor updated the Borough of Modena Council on the PEMA/FEMA Meredith Court mitigation project, saying the project began about four years ago and that project costs have increased since inception. Taylor said a cost analysis will be completed soon and that demolition work is scheduled to begin in August.
Taylor summarized project delays and rising costs and told councilors the borough will complete a cost analysis before advancing additional work. The minutes indicate the project has involved PEMA/FEMA; no specific dollar amounts were recorded in the minutes.
"Demolition will start in August," the minutes record. The council did not record a formal vote at the July 6 meeting to authorize additional funding; Taylor's update was presented as part of Old Business reporting.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.