D‑wing summer work may delay elevator completion by two to three weeks
Summary
Summer construction on the former Maple View 'D‑wing' will include HVAC, electrical and flooring work; a structural wall in the art lobby required shoring and may delay elevator completion by 2–3 weeks, though the wing should be accessible by school start.
Get email alerts on the Construction Facilities topic
No spam. Unsubscribe anytime.
Superintendent Dr. Francois updated the board on summer construction focused on the former Maple View 'D-wing.' Work planned for the summer includes HVAC upgrades, electrical improvements and installation of new flooring. Staff who may be relocating this fall are boxing classroom contents in preparation for the work.
A structural wall in the art lobby required shoring, which may delay the new elevator by two to three weeks, the superintendent said, but the wing is expected to be accessible by the start of school. Dr. Francois is coordinating with the Village to secure permits to vacate Center Street temporarily for construction of the loading dock this summer.
The timeline could affect classroom moves and contractor scheduling; the board did not take formal action but was informed of the expected delay and permit coordination.