After a report from Cody Thornton, the committee discussed arena electrical capacity and agreed to pursue a dedicated 3-phase service with its own transformer and meter rather than converting the entire facility; Wade will confirm voltage and amperage requirements with Hoyt and Tommy Joe.

The full story

Committee member Cody Thornton reported on an electrical-capacity review and recommended against converting the whole facility to 3-phase power. Instead, he said the preferred option is installing a separate, dedicated 3-phase service with an independent transformer and meter to meet expansion needs without disrupting the existing service.