District design team outlines schematic design, estimates for bond-funded school projects
Aug 20, 2026
Aug 20, 2026
Bond-funded schematic designs include restroom remodels, secure high-school vestibules, HVAC zoning and site utility upgrades; design team estimates roughly $2.5 million in construction for bid package one and recommends a 10% contingency.
The full story
Bond Architects principal Rebecca Clea and the district's design team presented schematic design work and cost estimates for the district's bond-funded capital projects, telling the board they are roughly 20–30% through design and preparing documents for a November bid.