CDBG WWTP improvements 83.6% complete; Parkhill awaits executed construction contracts
Jul 21, 2026
Parkhill's July report shows Project No. 40726.24 (CDBG WWTP improvements) at 83.61% complete; bid openings and recommendation-for-award letters were completed in April and pre-construction conferences were held May 27, 2026, but Parkhill is awaiting executed construction contracts.
The full story
Parkhill's progress report lists Project No. 40726.24 (CDBG WWTP Improvements) at 83.61% complete and records that the project was advertised, a mandatory pre-bid meeting held, and the bid opening completed with Recommendation for Award letters issued in mid-April 2026. A pre-construction conference took place May 27, 2026. Parkhill reported it is awaiting the executed construction contract to be returned to the City before construction can proceed fully.
Sign up to keep reading.
Your free newsletter brings you what your city council, county, and school board discussed and decided.
Keep reading for free
Create a free account to finish this story and see the video, transcript and key details.
Continue with GoogleContinue with emailAlready have an account? Log in →