CDBG WWTP improvements 83.6% complete; Parkhill awaits executed construction contracts

Jul 21, 2026

Parkhill's July report shows Project No. 40726.24 (CDBG WWTP improvements) at 83.61% complete; bid openings and recommendation-for-award letters were completed in April and pre-construction conferences were held May 27, 2026, but Parkhill is awaiting executed construction contracts.

The full story

Parkhill's progress report lists Project No. 40726.24 (CDBG WWTP Improvements) at 83.61% complete and records that the project was advertised, a mandatory pre-bid meeting held, and the bid opening completed with Recommendation for Award letters issued in mid-April 2026. A pre-construction conference took place May 27, 2026. Parkhill reported it is awaiting the executed construction contract to be returned to the City before construction can proceed fully.