Banks SD 13 bond update: program contingency at roughly $4.7 million (8.1%), above target

Banks SD 13 Work Session · March 10, 2026

Summary

Cornerstone told the board the bond program contingency across projects is about $4,707,000 (8.1%), exceeding the 5% target; a $58 million program budget and interest income were discussed and staff promised ongoing monthly updates.

Casey presented a program-level budget recap and contingency status, saying the program budget began near $58,000,002.24 and that interest earned has pushed the spendable total closer to about $59 million. "So we within both the 5 Star and PNC... those 4 numbers, as we stand today, is 4,707,000, which is 8.1%. Our goal before we start construction is to be above 5%." he said.

Board members asked about contract risk and how market pressures (tariffs, fuel) are being handled; contractors and staff said they are locking key materials early and structuring subcontract terms to reduce exposure. Casey said using some contingency to cover timely, cost‑effective wish-list items (including a proposed team-room shell) would keep the program above the target buffer.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source