Council hears multiple grant and infrastructure updates including Safe Routes, OSLAD and 1200 North work

Dec 8, 2025

City staff updated the council on storm sewer repairs (change orders for a water main break), Safe Routes to School Phases Two and Three, OSLAD grant procurement steps, 1200 North nearing substantial completion, and a $1.7 million local roads grant to fund downtown improvements.

The full story

City project manager Lee Beckman briefed the council on Dec. 8 about several ongoing and potential infrastructure projects. He said the storm sewer project required a change order after a water main break and that the contractor is expected to return next week with the project likely finishing in about two weeks. "The project remains under budget," Beckman said, and pay estimates were split to remain within bonding limits.