Commissioners approve $1.032 million plan to replace Reeds Mill Road bridge superstructure
Oct 8, 2024
Oct 8, 2024
Following an engineering review, Franklin County contracted Calderwood Engineering for a superstructure replacement of the Reeds Mill Road bridge at a quoted $1,032,000, with the board citing long-term lifecycle cost considerations.
The full story
County engineers presented two options for the Reeds Mill Road bridge: a superstructure rehabilitation that is roughly $160,000 less up front, and a full superstructure replacement. The board voted to pursue the superstructure replacement and contract Calderwood Engineering at a cost of $1,032,000.