Engineer reports ROWs secured for Phase II; sewer projects face scheduling and approval steps

Oct 28, 2025

Written engineer report: Phase II AMD/AML ROWs secured 28 of 34 and environmental assessment sent to Office of Surface Mining on Oct. 23; Chub Run sewer contractor start likely delayed to year-end; Phase IV sewer awaits PSC and DEP approvals for a connection at Sandy's Hardware station.

The full story

The engineer's written report summarized several infrastructure items. The Phase II AMD/AML project has right-of-way easements secured for 28 of 34 parcels and an environmental assessment was submitted to the Office of Surface Mining on Oct. 23, 2025; the engineer indicated the project is aiming to go out for bid by the end of the year. "Phase II AMD/AML Project: ROWs secured - 28 of 34; Environmental assessment submitted to Office of Surface Mining on 10/23/25; Aiming for project to go out for bid by end of year," the report states.