Citizen Portal

Get email alerts on the Capital Projects topic

No spam. Unsubscribe anytime.

River Ridge reviews gatehouse, monument and well plans; $2.5M loan likely

River Ridge Community Development District Board of Supervisors · April 28, 2026

Summary

Board reviewed a revised long-range plan that includes gatehouse renovations (FY2026 $615,775; FY2027 $407,240), monument replacements (~$250,000), and a backup irrigation well (~$291,500); staff said CIP changes may require a $2.5 million construction loan.

Board members reviewed a revised Long Range Plan outlining multiple neighborhood infrastructure projects, including monument replacements, gatehouse renovations and a backup irrigation well.

Eric Long described the completed traffic-calming project (radar sign and camera, $26,739) and said the backup irrigation well project is near completion with an additional estimated cost of $291,500. Long said the new well is expected to become the primary well after pump installation and planned water-quality testing. He said staff will remediate landscaping and sod damaged during construction contingent on coordination with a pending South Florida Water Management District stormwater project.

Long and District Engineer Charlie Krebs also presented cost estimates for monument replacements (probable cost about $250,000) and gatehouse renovations (estimated $615,775 in FY2026 and $407,240 in FY2027). Krebs noted the gatehouse project exceeds the sealed-bid threshold of $550,000, triggering a sealed-bid procurement process. District Manager reported the CIP changes will likely necessitate a construction loan of approximately $2.5 million; Chuck Adams said he will provide a term sheet for a $2.5 million loan with $50,000 costs of issuance at the next meeting.

Board discussion included timing, ownership of Corkscrew Road right-of-way, and aesthetic considerations. Board members directed staff to coordinate permitting and contractor selection and to pursue required Village of Estero permits and HOA coordination.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source