Manager: Pennvest waterline work progressing; pressure testing done on key streets

Monaca Borough Council · January 27, 2026

Summary

Manager David Kramer reported pressure testing is complete on Bechtel, Speyer and Front streets; most service-line work is on the hill and staging will move downtown once uptown work finishes. Bechtel service lines are not yet complete.

During his Jan. 27 report, Manager David L. Kramer Jr. updated council on the Pennvest-funded waterline work on Bechtel, Speyer and Front streets. He said "pressure testing remains completed on these streets," and that most service-line work is being done in the hill area.

Kramer told council that service lines on Bechtel Street are not yet complete and confirmed staging activity at Blaine Street, with plans to relocate staging downtown after further coordination. The manager also said monthly Pennvest meetings are being held to keep the project on task and to emphasize safety, particularly driver safety.

Council asked operational questions about sequencing and staging; Mr. Kramer responded with the current schedule but did not provide an estimated completion date in the minutes.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source