Town Hall site lacks base flood elevation; hydraulic analysis likely needed
Sep 8, 2025
Sep 8, 2025
Engineers could not establish a base flood elevation for the proposed Taghkanic Town Hall site; the town will need a hydraulic analysis (HEC‑RAS/HEC‑HMS) if it wants to model the 100‑year flood because DEC’s approach would require the first floor be set 3 feet above adjacent grade and no basement.
The full story
Supervisor Ryan Skoda reported Sept. 8 that Taconic Engineering (Andy Didio) relayed Crawford’s finding that it could not establish a base flood elevation (BFE) for the proposed new Town Hall site.
Sign up to keep reading.
Your free newsletter brings you what your city council, county, and school board discussed and decided.
or
Free account
Keep reading for free
Create a free account to finish this story and see the video, transcript and key details.
Continue with GoogleContinue with emailAlready have an account? Log in →