Boards set Fall 2029 target for new elementary; debate continues over Pre-K–5 vs. Pre-K–6

Jan 20, 2026

School and county representatives advanced the elementary-school project toward schematic design with a target completion of Fall 2029; participants debated whether the new building should serve Pre-K–5 (reducing footprint) or Pre-K–6, and discussed using existing high-school space for sixth grade.

The full story

Ms. Seay told the joint work session the new target completion date for the elementary project is Fall 2029 and outlined the immediate next steps: enter the full design phase, develop schematics, and select a construction manager while permitting and final design proceed concurrently. She noted site work has already begun with several site studies completed and clearing of the property under way.