Townsends Inlet Bridge fender work largely complete; new submarine cables ordered
Summary
Staff reported the Townsends Inlet Bridge fender system work is substantially complete, with only ladder installation and minor punch-list items remaining; new submarine cables have been ordered.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Project Manager Jason Futrell told the commission that fender-system work on the Townsends Inlet Bridge is substantially complete, with only ladder installation and a few minor punch-list items outstanding.
Futrell also reported that "the new submarine cables have been ordered." The minutes do not specify a delivery date for the cables or budget revisions related to the remaining work.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.