Engineering report: Phase 1 pay application near ready; Phase 2 ROWs and Chub Run timelines updated
Summary
Town engineers reported Phase 1 AMD pay-application comments are nearly complete and expected to be drawn down at the September meeting; Phase 2 has 20 of 34 ROWs in hand and awaits environmental clearance from OSM, while Chub Run remains on hold with a potential Oct. 1 start.
Get email alerts on the Infrastructure Projects topic
No spam. Unsubscribe anytime.
Town engineering staff provided a multi-item update on capital projects Aug. 26. Phase 1 AMD is nearing completion of pay-application comments and should be ready for drawdown at the Sept. meeting; Phase 2 AMD has 20 of 34 right-of-way acquisitions in hand and is awaiting environmental assessment clearance from the Office of Surface Mining (OSM) before proceeding to bid. Chub Run remains on hold with a potential Oct. 1 start date discussed.
The report also noted Phase IV work is awaiting environmental clearance from the West Virginia Department of Environmental Protection related to Sandy's Hardware forcemain work. Nutter Run permitting (Task Order #7) was also referenced as complete in the engineering updates.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.