Engineering report: Phase 1 pay application near ready; Phase 2 ROWs and Chub Run timelines updated

Aug 26, 2025

Town engineers reported Phase 1 AMD pay-application comments are nearly complete and expected to be drawn down at the September meeting; Phase 2 has 20 of 34 ROWs in hand and awaits environmental clearance from OSM, while Chub Run remains on hold with a potential Oct. 1 start.

The full story

Town engineering staff provided a multi-item update on capital projects Aug. 26. Phase 1 AMD is nearing completion of pay-application comments and should be ready for drawdown at the Sept. meeting; Phase 2 AMD has 20 of 34 right-of-way acquisitions in hand and is awaiting environmental assessment clearance from the Office of Surface Mining (OSM) before proceeding to bid. Chub Run remains on hold with a potential Oct. 1 start date discussed.