Council hears engineering updates: AMD phases, Chub Run, forcemain and Edison retaining wall
Summary
Engineers reported pay-application comments addressed for Phase I AMD, Phase II AML design submitted with 28 of 34 ROWs secured, Chub Run start set for Nov. 1, 2025 with a forthcoming time-extension change order, and Phase IV forcemain work awaits WVDEP environmental clearance.
The council received an engineering report covering multiple projects. For Phase I AMD, pay-application 4 comments were addressed and sent to AML; Phase II final AML design was submitted with 28 of 34 right-of-way parcels in hand and the environmental assessment pending, with a target to be out to bid by year-end. The Chub Run project is scheduled to begin Nov. 1, 2025, and an upcoming change order for a time extension will be presented next month.
Phase IV work (forcemain) is awaiting environmental clearance from the West Virginia Department of Environmental Protection (WVDEP), and the town is preparing an engineering contract for the Edison retaining-wall project. The engineering report indicated additional amendments and requisition timing may require a special meeting depending on approvals.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.