Reserve Township approves $11,621.04 final payment to Robinson Pipe Cleaning and a $6,785.70 contract decrease

Nov 5, 2025

The board approved Change Order No. 1 reducing the 2025 CCTV contract by $6,785.70 and authorized Payment Request No. 2 (final) to Robinson Pipe Cleaning for $11,621.04 for the 2025 Operations & Maintenance CCTV Project.

The full story

The Reserve Township Board approved three related actions on the 2025 Operations and Maintenance CCTV Project. First, the board approved Change Order No. 1 for Robinson Pipe Cleaning representing a decrease of $6,785.70 to the contract. Commissioner Sharon Sweeney moved the change order; Commissioner Rob Stephens seconded, and the motion carried.