Board accepts closeout documents, payment application and cost reduction for Albion Northwest Road Project

Boone County Board of Commissioners · August 10, 2026

Summary

The Boone County Board accepted Change Order #1 lowering cost by $8,827.07, approved Payment Application #4 for $62,617.44, and accepted a Certificate of Substantial Completion (July 23, 2026) for the Albion Northwest Road Project.

The board reviewed closeout documents from A&R Construction Co. for the Albion Northwest Road Project. Change Order #1 reduced the contract cost by $8,827.07; Payment Application #4 requested $62,617.44; and a Certificate of Substantial Completion indicated the project was completed in full as of July 23, 2026. Commissioner Matt Niewohner moved and Commissioner Brian J. Yosten seconded acceptance of the documents and authorization for the chairman to sign.

With the board’s acceptance, the county recorded project closeout actions and authorized document signatures to process payment to the contractor per the terms presented.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.