Maple Street paving delayed to spring 2026 after contractor request

Dec 1, 2025

Council recorded a contractor request to postpone the final 1.5-inch mill and overlay on Maple Street until spring 2026; the borough engineer approved the extension and the remaining paving is expected to be completed by April 26, 2026. Council will follow up on plans from Greenman-Pedersen, Inc.

The full story

Councilmember Marc Gaughan described a miscommunication between Stafursky Paving and RLE Enterprises about the Maple Street Paving Project and relayed an email chain forwarded by borough engineer Robert J. Bochicchio of Greenman-Pedersen, Inc. RLE Project Manager Todd Cantafio requested permission to complete the remaining 1.5-inch mill and overlay in spring 2026; the request was approved and RLE now anticipates completion by April 26, 2026.

Free newsletter

Sign up to keep reading.

Your free newsletter brings you what your city council, county, and school board discussed and decided.

or
Already have an account? Sign in