Committee approves multiple PCOs and floor-prep holds for the Wakefield project

Permanent Building Committee · August 25, 2026

Summary

Contractor and project staff presented a series of PCOs (interim change orders) covering TV display revisions, an overhead door, floor marking remediation, HVAC and telecom adjustments and several floor-prep items; the committee approved the set of change orders and several T&M floor-prep holds.

Project staff and contractor representatives reviewed a sequence of PCOs (project change orders) and related time-and-material holds. Items included small credits (for deleted TV locations) and added-cost items such as an overhead door ($7,000), floor-marking removal ($82,491), select HVAC/telecom work ($19,337) and other mechanical and finish adjustments. The presenter explained each PCO's scope and the committee moved to approve internal change order number 27 and related PCOs as presented.

Separately, the committee approved several floor-prep hold releases and associated PCOs in modest dollar amounts (examples: PCO 760 for $5,160; PCO 764 for $5,265; PCO 765 for $3,287) to address localized concrete and tile prep, terrazzo transitions and shower-floor transitions. Staff said these PCOs originated from held floor-prep allowances and described sequencing constraints among trades as the reason for staged work.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source