Developer says Nanisca thermal storage and local solar projects on track for fall commissioning

Aug 24, 2026

Developer and project managers told the commission solar panels are installed and the thermal‑storage line will begin construction in early September, with a formal commissioning event planned and a route amendment for Southeast 70th Ave to be filed after kickoff.

The full story

A developer representative and project managers updated the commission on two energy projects: a nearly completed solar project with panels installed and an energization process underway, and the Nanisca Thermal Storage project where construction mobilization is expected in the first–second week of September.