Webster Groves advisory panel hears $1 million estimate for parking-deck repairs, staff plans phased spring work

Aug 25, 2026

City staff reported engineering is complete for the downtown parking deck, with construction bids slated for fall and work likely in early spring; the estimated cost is about $1,000,000 and phasing may keep parts of the deck open during repairs.

The full story

City staff told the Webster Groves Special Business District Advisory Commission that engineering work on the downtown parking deck is finished and construction bidding will begin this fall. The staff representative said the project is expected to start in early spring and could take about three months if done in a single phase.