Committee backs biosolids drying system plan; estimated capital cost $12.56 million

Jun 16, 2026

Consultant recommendation to install an Indirect Heat-Auger dryer with rotary press dewatering unit was forwarded to the Village Board and to WDNR for approval; estimated capital cost is $12,562,300 and construction is projected for 2028–2029.

The full story

The Finance Committee recommended forwarding the Wastewater Treatment Facility Biosolids Handling Facilities Modifications Plan — recommending an Indirect Heat-Auger dryer with a rotary press dewatering unit — to WDNR for approval and to the Village Board for subsequent design and construction approvals. "Indirect Heat-Auger Dryer with Rotary Press Dewatering Unit" is listed as the recommended plan in presentation materials.