Board hears high school construction update; seismic work largely complete

Ashland School District 5 Board of Directors Regular Session · August 14, 2025

Summary

Executive Director of Operations Steve Mitzel and HMK Project Director Josh Whitaker told the board that the chiller and gym gear are installed, most seismic retrofit work is finished, and remaining items include shade sails, a kiosk and parking lot striping.

Executive Director of Operations Steve Mitzel and HMK Project Director Josh Whitaker updated the Ashland School District 5 Board on the high school construction status, reporting that "the chiller and gear installation in the high school gym" is complete and that most seismic retrofit construction is now finished. Interior spaces are being turned over to teachers as areas are cleared for use.

Mitzel and Whitaker said remaining work includes installation of shade sails on the quad, a kiosk, and parking lot striping to finish site access. The project team described the sequenced turnover of interior spaces to allow instruction to resume in updated classrooms. No formal action or new funding requests were presented at the meeting; the update was informational and followed the district's bond schedule.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source