ECISD board hears Bond 2023 progress: $51M spent so far, major projects underway
Aug 19, 2025
Ector County ISD trustees received a Bond 2023 update reporting roughly $51 million spent, key construction milestones (new West Odessa middle school ~21% complete), and major equipment orders including 1,408 musical instruments (1,080 received). The board approved multiple bond-related contracts and purchases.
The full story
Ector County ISD trustees heard a detailed progress report on the district's Bond 2023 program on Aug. 19, with Associate Superintendent Dr. Anthony Sorola and CFO Albessa Chavez laying out construction and procurement milestones. The board was told the new West Odessa middle school is approximately 21% complete, building pads for the Career & Technical Education center are nearly finished, and the district has spent about $51 million to date with an additional $199 million encumbered through requisitions.
Sign up to keep reading.