District engineers reported all four drainage sites are under construction with pipes installed, sod installation expected the week of July 2 and project completion anticipated by the end of July; 12 trees in Palmetto Dunes and six Cabbage Palms in Oak Run will be removed and replanted.
The full story
District Engineer Charlie Krebs told the River Ridge board June 23 that all four drainage improvement sites are under construction: "sites are cleared and silt fences were installed," pipe has been installed in places and fill is being staged at Turnberry.