Pumping Station project delayed; council asks USDA documentation before approving $80,430 inspection amendment

Nov 5, 2025

GMB engineers reported the pumping station project is running behind and proposed an amendment for up to $80,430 in full‑time inspection services required by USDA. The council tabled the amendment pending documentation from USDA and expects to revisit the item in December.

The full story

Engineers from GMB told the Trappe council that the Pumping Station project, scheduled for substantial completion Nov. 29, 2025, is running behind and likely will not reach final completion until January 2026.